Renovation work begins on the former Agricultural Bank in Targovishte

Renovation work begins on the former Agricultural Bank in Targovishte

Renovation work begins on the former Agricultural Bank in Targovishte. The restoration of the building, constructed in 1915, will cost nearly 4.5 million leva, funded from the state budget. The renovation work will take 14 months. This was announced at a briefing today by the mayor, Dr Darin Dimitrov, and the director of the ‘Urban Planning’ department…

Renovation work begins on the former Agricultural Bank in Targovishte

The restoration of the building, constructed in 1915, will cost nearly 4.5 million leva, funded from the state budget. The renovation work will take 14 months. This was announced at a briefing today by the mayor, Dr Darin Dimitrov; the director of the ‘Spatial Planning and Infrastructure’ department at the municipality, Eng. Svetlana Deyanova; and Eng. Donche Raicheva from the contractor ‘Stroykomers-TT’.

“The aim is for the building to be converted into exhibition halls following the refurbishment, so that we can use it for joyful events and ceremonies. It will remain municipal property so that all our fellow citizens can visit it”, said the mayor, Dr Dimitrov.

He also officially handed over the documents for the opening of the construction site to the contractor.

The project aims to restore the building’s architectural and artistic features to the greatest possible extent, explained Eng. Svetlana Deyanova from Targovishte Municipality.

“The building has the characteristic appearance of public buildings from the early 20th century – with numerous elements and ornaments on the façade and roof, and a lavish interior. The total area to be refurbished is approximately 800 square metres. On the ground floor, there will be an exhibition hall, a security office, corridors and toilets. On the first floor, there will be administrative offices and a staff room,” said Deyanova.

She explained that the terms of the public tender stipulate that the contractor must work with a conservationist and a restorer.

“The law does not require this. However, we have nevertheless included these conditions to ensure that we preserve the architectural appearance of the building to the greatest possible extent,” explained Eng. Deyanova.

Preparations are also beginning on the construction site, including the delivery of materials and the fencing off of the site, with these activities expected to take around a month, explained Eng. Donche Raicheva from “Stroykomers-TT”.

“The construction work will begin with the reconstruction of the roof, followed by work on the structure, the building services, the restoration of the window and door frames, and the architectural elements in the exterior and interior,” explained Eng. Raicheva.



Professional ties