In sections ‘B’ and ‘C’ of the Popovo General Hospital building, a two-month refurbishment has been completed and a ‘Covid’ ward has been established, featuring two entirely new separate entrances.
The designated area has undergone a comprehensive major refurbishment, both internally and externally, and supporting infrastructure has been installed (toilets, staff rooms, storerooms and the necessary laboratories).
The entire water supply system has been replaced; new water pipes and floor-level drainage systems have been installed; the electrical system has been refurbished; and the lighting fixtures have been replaced.
New antibacterial floor coverings have been installed.
The contracting authority and project partner is Popovo Municipality; the project was implemented under the ‘Regions in Growth’ Operational Programme, with the Ministry of Health as the specific beneficiary.
The value of the construction and installation works carried out is 174,185.77 BGN excluding VAT.