Targovishte Municipality is to implement a 4.3 million leva project to reclaim the first cell of the landfill near the village of Paidushko
Targovishte Municipality has signed a contract to fund a project for the reclamation of the first disused cell at the household waste landfill near the village of Paidushko. It will be implemented under the ‘Environment’ Programme 2021–2027.
The total cost of the project is 4.36 million leva. Of this, 3.47 million leva is grant funding, whilst over 885,000 leva is provided by the municipality itself.
The total area of the cell is over 40 decares.
The work involved in establishing the landfill site will take place in two phases – the technical part of the project involves the construction of a system for wastewater disposal and landfill gas capture, with a duration of 24 months, and the biological reclamation phase, which will involve landscaping the site and post-operational maintenance – with a timeframe of up to 36 months following the completion of the first phase.
Construction of the second cell is ongoing. At the end of May, the mayor, Dr Darin Dimitrov, signed an agreement with the Ministry of Regional Development and Public Works for the provision of 3.7 million leva to complete the construction.
According to data from the municipality