MODERA HOUSE has launched an innovative production facility for prefabricated timber houses in the town of Targovishte. On 1 December 2025, in the industrial zone of Targovishte, at an official ceremony, MODERA HOUSE commenced operations by presenting modern technology for the production of prefabricated timber houses…
MODERA HOUSE launches an innovative production facility for prefabricated timber houses in the town of Targovishte
On 1 December 2025, in the industrial zone of Targovishte, at an official ceremony, MODERA HOUSE commenced operations by presenting modern technology for the production of prefabricated timber houses, combining speed, quality and environmental sustainability.
The company, which is part of the furniture manufacturing enterprise ‘Mebel Stil’ Ltd, Targovishte, utilises state-of-the-art PREFAB technology in its production process, a method successfully applied in Western Europe.
The company’s main objectives are to provide customers with a high-quality product, manufactured in a controlled factory environment, with a high degree of pre-fabrication and significantly reduced lead times.
Presentation
The presentation was delivered in a modern style– the offices and showroom are located within the production facility, enabling customers to select all the details for their future home within a few days and discuss their ideas with designers.
There is the option to remotely monitor the production process via cameras in the production hall and on the building site, allowing the client to view in real time, from their mobile phone, the sequence of activities and the stages their order is going through.
Customers can choose between ready-made house designs or bespoke designs tailored to their specific requirements. Each project is adapted to suit the specific characteristics of the plot in question.
Environmental friendliness and sustainability, durability and reliability
This type of construction is characterised by a significantly lower carbon footprint.
MODERA HOUSE uses timber from sustainably managed forests. The insulation is made from recycled paper or wood fibres, materials with a significantly lower energy consumption during production. Timber structures are lighter and more resistant to seismic forces.
Production process
Production takes place in a factory setting, with up to 90 per cent of the work completed off-site.
Over 70 per cent of the production processes are automated, ensuring standardised quality and precision in execution.
The company operates a complete production line for timber-framed panels under the WEINMANN and ISOCELL brands.
The manufacturing process involves four specialised machines: a beam processing system and two assembly tables: the first for the structure and internal layers, the second for flipping, filling with insulation and fitting the external elements, as well as an insulation filling system.
Completion times
A guaranteed, significant reduction in the traditional construction project timeline is stated – the period from the issue of the building permit to handover is specified as between two and three months.
Quality control
The company has CNC machines, which ensure product standardisation.
An individual file is created for each house, documenting the results after each stage of production. The timber structure is calculated in accordance with the specific site conditions, taking into account climatic factors, seismic requirements, and snow and wind loads.
Vision for Development
MODERA HOUSE plans to gradually reach the full capacity of its production line through its own projects and the manufacture of panels for subcontractors.
The technological infrastructure allows for expansion into modular construction, with plans to produce wet rooms as ready-made modules, and, in the long term, combinations of panels and various types of modules in line with market demand.
The company is already in negotiations to participate in the construction of eco-villages and larger-scale projects, including mass production.
Among the official guests at the opening were the Regional Governor, representatives of the Bulgarian Chamber of Builders – Targovishte Regional Branch, as well as a number of business partners from across the country.
Related articles
Галерия
ОП Търговище
Проекти в процес на реализация, финансирани със средства от Европейския съюз към 1 януари 2014 г.
Проекти в процес на реализация, финансирани със средства от Европейския съюз към 1 януари 2014 г. № по ред № и дата на договора за БФП/ на проектното предложение Опера-тивна програма Предмет/обхват на договора за БФП/ на проектното предложение Проекти в процес на реализация 1 Договор…